REPLACEMENT OF EXISTING ABURA 8S&L FLOWLINES WITH 4” SCHEDULE 80 FLOWLINES IN OML 65

NAME OF PROJECT

  • Replacement of Existing Abura 8S&L Flowlines with 4” Schedule 80 Flowlines in OML 65.

CLIENT

PROJECT STATUS

COMPLETED

LOCATION

Abura OML 65, Delta State.

PROJECT SCOPE

Edemx Energy International Limited executed the Replacement of Existing Abura 8S & L Flowlines With 4” Schedule 80 Flowlines in OML 65. OML 65 is an onshore block in the western axis of Niger Delta, containing one producing field: Abura. Abura has being in production since 1978. The scope of work includes:
  • Supply of pipe bends, elbows, flanges, gaskets, bolts, nuts and other pipeline construction accessories
  • Transportation of 1,900 Joints of 4” Sch. 80 PE Coated Line-pipes
  • Provide for the Clearing of Marshy/Swampy and Bushy Sections of the ROW
  • Stringing, Beveling, Welding and Field Wrapping of 1900 joints of 4” schedule 80 PE Coated Line-pipes
  • Trench excavation, Lowering and Backfilling of Abura 8S & L Flowlines routes
  • Complete Road Repair and Thrust boring through Major Roads
  • Manifold Tie-ins
  • Well Head and Manifold Hook – up Assembly
  • X-Radiography and Pressure Testing
  • Provision of Temporary Cathodic Protection system
  • Provision of Project management tools and as built drawings
  • Commissioning of the newly constructed Flowlines
  • De-commissioning of the Old Flowlines and Transportation to NPDC Warehouse.